In a hybrid project, two key stakeholders have conflicting requirements regarding the frequency of reporting. One prefers highly detailed weekly reports, while the other wants only a high-level monthly dashboard. The project manager brings them together to find a solution that satisfies both needs without increasing the team's administrative burden. Which conflict resolution technique is being applied?