A project manager is in the process of validating scope with the customer for a software upgrade project funded by a fixed-price contract. The customer agrees that all requirements in the scope statement were met but refuses to sign off, claiming the user interface 'doesn't feel right.' What document should the project manager use to defend the project's completion?